Councils accessing GRQ funding may occasionally require additional time to submit acquittal documentation or wish to rollover unspent funds into the next financial year. 

The following outlines the process for extension of time and funding rollover.

1. Extension of time

If a council anticipates lodging acquittal documentation after the deadline (30 September 2026), they may request an extension.

Key points:

  • Request must be submitted in writing, providing reasons for late lodgement.
  • Approval is required from the Get Ready Queensland and QRA's Portfolios.
  • This does not extend the timeframe for using the allocated funding. Councils must still complete activities and use funds within the current financial year.
  • Funding for the current year must still be closed out by 30 September 2026.
  • All requests to be emailed to getready@qra.qld.gov.au

 

Extension of time process table  

StepActionResponsible partyNotes
1Prepare a written request for extensionCouncilInclude reasons for late lodgement
2Submit request to Get Ready teamCouncilApproval required from Portfolios
3Approval outcome communicatedGet Ready QueenslandCouncil notified of new acquittal lodgement date
4Lodge acquittal by new approved dateCouncilFunding activities must still be completed within original timeframe

2. Rollover of funding

Councils may request to rollover unspent funding if they cannot utilise all funding by 30 June 2026.

Key points:

  • Request must be submitted in writing, signed by a delegated officer.
  • Reasons for rollover should be clearly outlined (e.g., impacted by severe weather events).
  • Rolled-over funds are added to the council’s allocation for the following financial year.
  • Councils must plan activities based on the total available funding (current year + rollover).
  • Final acquittal will reflect the higher total funding including rollover.
  • All requests to be emailed to getready@qra.qld.gov.au

 

Example scenario:

DescriptionAmount
Current year allocation$4,880
Amount spent$2,880
Unspent balance$2,000 (requested for rollover)
Next year allocation$4,880 + $2,000 rollover = $6,880
Payment90% upfront of new allocation minus previous year rollover (system adjusts automatically)
AcquittalFinal progress report lodges total $6,880 showing full utilisation

 

Rollover process table

StepActionResponsible partyNotes
1Identify unspent fundsCouncilReview current year expenditure
2Prepare written rollover requestCouncilMust be signed by delegated officer, include reasons
3Submit request to Get Ready teamCouncil Approval required
4Approval processed in systemGet Ready Queensland Rollover amount allocated in MARS system for council’s GRQ program
5Plan activities for next financial yearCouncilInclude rollover in planning ($ current year + rollover)
6Receive paymentCouncil90% upfront; system deducts previous rollover if applicable
7Lodge final acquittalCouncilDemonstrate full utilisation including rollover
8Assessment completedQRA Assessments teamAssessment considers total funding (original + rollover)

Notes:

  • All requests (extension or rollover) must be submitted in writing and emailed to getready@qra.qld.gov.au and approved before deadlines.
  • Rollover requests do not affect current year deadlines for completion of activities.
  • Councils are responsible for closing out all funding and reporting accurately, including any rollover amounts.